Meeting 25 February 2016, 2pm

Attended:

Agenda:

  • Progress on Milestones
  • Timeline
  • Brief summary since the last meeting

Progress on Milestones:

  • Testing Failover: Daniel renamed the item with the milestone to "INITIAL testing failover" which is complete. So, done.
    • Further failover testing has to happen with sample data; we already have an item for testing Inventory with failover (without a milestone).
  • Backups set up and tested: (Schedule says due today): Fraser has made progress.

Timeline

  • Keeping to the schedule set last week:
    • Fraser and Daniel are moving/testing inventory- likely not finished until mid-next-week (not today as Daniel emailed out).
    • Schedule shows wrapup March 17 (a day later than last week).

Brief summary since the last meeting

  • Dave has confirmed the interfaces on the machines is currently capable of 10Gb to the rest of CS.
  • Anthony's docs are linked from the Mysql page
  • Daniel investigated clients of the database; assuming www.cs, www.math, and linux.cscf are the only hosts we need to flush DNS cache.

Next Meeting

  • Thu 3 Mar - room is back to DC2310

-- DanielAllen - 2016-02-25

Edit | Attach | Watch | Print version | History: r2 < r1 | Backlinks | Raw View | Raw edit | More topic actions...
Topic revision: r1 - 2016-02-25 - DanielAllen
 
This site is powered by the TWiki collaboration platform Powered by PerlCopyright © 2008-2025 by the contributing authors. All material on this collaboration platform is the property of the contributing authors.
Ideas, requests, problems regarding TWiki? Send feedback