Meeting 25 February 2016, 2pm
Attended:
Agenda:
- Progress on Milestones
- Timeline
- Brief summary since the last meeting
Progress on Milestones:
- Testing Failover: Daniel renamed the item with the milestone to "INITIAL testing failover" which is complete. So, done.
- Further failover testing has to happen with sample data; we already have an item for testing Inventory with failover (without a milestone).
- Backups set up and tested: (Schedule says due today): Fraser has made progress.
Timeline
- Keeping to the schedule set last week:
- Fraser and Daniel are moving/testing inventory- likely not finished until mid-next-week (not today as Daniel emailed out).
- Schedule shows wrapup March 17 (a day later than last week).
Brief summary since the last meeting
- Dave has confirmed the interfaces on the machines is currently capable of 10Gb to the rest of CS.
- Anthony's docs are linked from the Mysql page
- Daniel investigated clients of the database; assuming www.cs, www.math, and linux.cscf are the only hosts we need to flush DNS cache.
Next Meeting
- Thu 3 Mar - room is back to DC2310
-- DanielAllen - 2016-02-25