Meeting 3 March 2016, 2pm
Attended: drallen a2brenna fhgunn
Agenda:
- Progress on Milestones
- Timeline
- Brief summary since the last meeting
Progress on Milestones:
- Backups set up and tested: (Due-date reset to today): Remaining: testing restore of master? (is this different from restoring slave?)
Timeline
- moving inventory- likely not finished until Friday (18th), with more testing done in the meantime.
- Schedule has had further slip, shows wrapup April 7 or so where:
- Mon 14 Mar - Fri 18 Mar is moving inventory (Fraser and Daniel);
- Mon 21 Mar - Wed 23 Mar is moving the rest of apps (Fraser and Daniel);
- Thu 24 Mar - Wed 29 Mar is benchmarking apps (Lori and Daniel);
- Tue 22 Mar - Tue 29 Mar is finalizing monitoring, tuning, maintenance documentation (Anthony, Fraser, Daniel) - Fraser only available until 24th. (here the following week but realtime lab may interfere).
- Tue 29 Mar - Thu 7 April is wrapup: Fixing remaining issues, writing up lessons learned, proposed plans for student cluster, handoff to Ken.
Brief summary since the last meeting, and upcoming week ("this week")
-- DanielAllen - 2016-03-17