Meeting 3 March 2016, 2pm
Attended: drallen a2brenna fhgunn ldpaniak
Agenda:
- Progress on Milestones
- Timeline
- Brief summary since the last meeting
Progress on Milestones:
- Backups set up and tested: (Due-date reset to today): Remaining: testing restore
Timeline
- moving inventory- likely not finished until Friday (11th), a few days more slip.
- Schedule shows wrapup April 4 (!) where:
- Mon 14 Mar - Fri 18 Mar is moving the rest of apps (Fraser and Daniel);
- Fri 18 Mar - Tue 22 Mar is benchmarking apps (Lori and Daniel);
- Tue 22 Mar - Tue 29 Mar is finalizing monitoring, tuning, maintenance documentation (Anthony, Fraser, Daniel) - Fraser only available until 25th.
- Tue 29 Mar - Mon 4 April is wrapup: Fixing remaining issues, writing up lessons learned, proposed plans for student cluster, handoff to Ken.
- Can we gain time back?
Brief summary since the last meeting, and upcoming week ("this week")
-- DanielAllen - 2016-03-09