±Meeting 18 February 2016, 2pm
Attended:
Agenda:
- Progress on Milestones
- Timeline
- Brief summary since the last meeting
Progress on Milestones:
- Testing Failover: Was 17 Feb. Decided it can be done in parallel; work in process- Reset to be due tomorrow (19 Feb).
- Backups set up and tested: (Monday 22 Feb) is started by Guoxiang.
Timeline
- Keeping to the schedule set last week:
- started moving first database (inventory) yesterday Feb. 17
Brief summary since the last meeting
- Anthony has brought up mysql-106.
- Networking is not 40GB yet - but Devon has done necessary hardware upgrade; at least a week away (?)
- Setting up backup is started but not complete; Guoxiang has completed his part; Fraser has configuration of Percona remaining
- Daniel has set up nagios monitoring for mysql-102.
- Fraser and Daniel doing a sync of inventory including the same process (and same data transfer) as stage two sync; this will give us timing on the stage two move.
- if things go very well, Fraser and I may be able to start moving the rest of databases starting Wednesday Feb. 24, though schedule suggests Fri. Feb 26 - Tues. Mar 1 (CSCF staff meeting).
Next Meeting
- Thu 25 Feb - NOTE ROOM CHANGE: DC 2564
-- DanielAllen - 2016-02-17